CONSTRUCTION UPDATE: JAN
Construction on site continues to advance well, installation of panels is now complete in the North half of the site and resources continue to ramp up to progress according to schedule.
Delivery of all piles, tracker equipment and modules is now complete.
Installation and delivery of Power Conversion Units has commenced and will continue over the weeks to follow.
High Voltage (HV) transformer foundation works and substation trenching is now complete. HV transformers have been delivered to site, set in place and are being fitted out.