Neoen acknowledges the Yorta Yorta people, Traditional Owners of the land on which Numurkah Solar Farm harvests the energy of the sun. We pay our respects to their Elders past and present.
20190130 article construction update jan

CONSTRUCTION UPDATE: JAN

Construction on site continues to advance well, installation of panels is now complete in the North half of the site and resources continue to ramp up to progress according to schedule.

Delivery of all piles, tracker equipment and modules is now complete.

Installation and delivery of Power Conversion Units has commenced and will continue over the weeks to follow.

High Voltage (HV) transformer foundation works and substation trenching is now complete. HV transformers have been delivered to site, set in place and are being fitted out.

Hv station 25 jan 2019 v4 367x206 1
HV transformer installation
Drone 12 jan 2018 367x274 1
Mechanical Installation Progress