Farm in operation

Farm in operation

Farm in operation The Numurkah Solar Farm will generate 255 GWh of emission-free, clean, competitive renewable energy per annum to power key infrastructure such as the Melbourne tram network and Laverton steel works The support of the Victorian government was...
Construction update: May

Construction update: May

Construction update: May The Solar farm is mechanically complete. Demobilisation of contractors is underway. The commissioning of the Solar farm is ongoing. North side mechanically complete South side mechanically...
Construction update: Apr

Construction update: Apr

Construction update: Apr The substation was successfully energised. The mechanical installation of trackers and modules is now complete. Most of the mechanical contractors on site have now demobilised. The online commissioning of Power Conversion Units is ongoing....
Construction update: Feb

Construction update: Feb

Construction update: Feb Construction on site advanced well during the month of February. The mechanical installation of piles is nearly complete. The mechanical and electrical installation of tracker and module equipment is on target for completion by the end of...
Construction update: Jan

Construction update: Jan

Construction update: Jan Construction on site continues to advance well, installation of panels is now complete in the North half of the site and resources continue to ramp up to progress according to schedule. Delivery of all piles, tracker equipment and modules is...